//Case · 2023 · Amsterdam Centraal

UPS installation placed at Amsterdam Centraal station

First Case handled transport, placement and mechanical installation of two 200 kVA Schneider Easy 3M UPS systems with battery cabinets at Amsterdam Centraal station. Ten pallets of material, 92 battery blocks and bypass panels, delivered install-ready within the windows of a live station.

//Amsterdam CS

UPS installation placed at Amsterdam Centraal station

Two 200 kVA Schneider UPS systems with 92 battery blocks, placed install-ready at Amsterdam Centraal.

Request a quote
//The brief & what we delivered

Get two complete UPS systems safely on site and place them install-ready, inside a working station.

A UPS installation at Amsterdam Centraal leaves no room for improvisation: the supply chain has to be right and the station stays operational. Two 200 kVA UPS systems, two battery cabinets and 92 battery blocks had to arrive on site heavy, complete and in the correct order. Schneider wanted one party for transport, placement and mechanical installation, so its own engineers only had to connect and commission. Work on weekdays only, within fixed windows.

The scope: ten pallets through warehouse inbound and outbound, transport within the delivery radius and on-site installation of batteries, bypass panels, breakers and sensors. Lead time around five weeks after order, handed over install-ready for Schneider.

Location
Amsterdam Centraal
Client
Schneider
System
2× 200 kVA UPS
Batteries
2 strings · 92 blocks
Logistics
10 pallets
Service
Installation
The full work package05 components · one point of contact

Transport

Material moves through warehouse inbound and outbound to site, within the delivery radius and fixed windows.

Placement

Two 200 kVA UPS systems and two battery cabinets are set in their final position.

Batteries

Per cabinet a string of 46 battery blocks is placed and mechanically mounted.

Bypass

Bypass panels are hung and the battery breakers mounted in the cabinets.

Wiring

Internal wiring, temperature sensors and network cards are fitted and connected.

SITE · AMSTERDAM CSSUPPLY ROUTELOGISTICS & SUPPLY10× PALLET10 PALLETS · INBOUND & OUTBOUNDFIRST CASEFC-2301-01UPS INSTALLATION01 · LOGISTICSSCHAALISO
//Logistics

Ten pallets staged and supplied in order

Before anything goes on site, the goods run through warehouse inbound and outbound. Ten pallets are checked, bundled and staged in the right order. Transport happens within the delivery radius and on the agreed reception slots.

01Inbound and outbound of ten pallets in the warehouse
02Supply within the fixed delivery radius
03Delivery on fixed days, within work windows 07:00-17:00
//Placement

UPS systems, cabinets and 92 battery blocks in place

On site, two 200 kVA UPS systems and two battery cabinets are set in their final position. Each cabinet takes a string of 46 battery blocks, mechanically mounted and in sequence. The heavy material is brought in over a level, clear floor.

01Two 200 kVA UPS systems placed
02Two strings of 46 battery blocks in the cabinets
03Access route free of obstacles and level differences
92 BLOCKS · 2 STRINGSPLACEMENT & INSTALLATION92 BLOCKS · 46/STRING2× 200 kVA UPS · 2 CABINETSFIRST CASEFC-2301-02UPS INSTALLATION02 · PLACEMENTSCHAALISO
TEMP SENSORNETWORK CARDBYPASS PANELBREAKERBREAKERBREAKERINSTALL-READYFINISHING & HANDOVERBYPASS · SENSORS · INSTALL-READYFIRST CASEFC-2301-03UPS INSTALLATION03 · FINISHINGSCHAALISO
//Finishing

Bypass, sensors and wiring, handed over install-ready

Finally, the bypass panels are hung and the battery breakers mounted. Temperature sensors, network cards and internal wiring are fitted and connected. The whole is handed over install-ready, so Schneider only has to connect and commission.

01Bypass panels hung, breakers mounted
02Temperature sensors and network cards fitted
03Internal wiring connected, handed over install-ready
//The lead time

From order to install-ready handover

A fixed flow: procure, supply, place, install, hand over.

View UPS Installation
01After order

Lead time around 5 weeks

Material is ordered and staged, lead time around five weeks.

02Warehouse

Inbound and outbound

Ten pallets staged through warehouse inbound and outbound.

03On site

Placement

Two UPS systems and two battery cabinets set in position.

04On site

Installation

Batteries, bypass panels, breakers and sensors installed.

05Handover

Install-ready

Internal wiring connected and handed over install-ready.

The systems stood complete and in the right place when we connected. One party for transport and installation saves us coordination and on-site risk.

Project lead · Schneider
//cases

Other cases

View all cases
//The brief

Get two complete UPS systems safely on site and place them install-ready, inside a working station.

Two 200 kVA UPS systems, two cabinets and 92 battery blocks, complete and in order at a working station. One party for transport, placement and installation.

Ten pallets through the warehouse, lead time around five weeks, handed over install-ready.

Location
Amsterdam Centraal
Client
Schneider
System
2× 200 kVA UPS
Batteries
2 strings · 92 blocks
Logistics
10 pallets
Service
Installation

The full work package

One party handles supply, placement and mechanical installation, install-ready.

Transport
10 pallets supplied
+

Material moves through warehouse inbound and outbound to site, within the delivery radius and fixed windows.

Placement
2× 200 kVA UPS
+

Two 200 kVA UPS systems and two battery cabinets are set in their final position.

Batteries
2 strings · 92 blocks
+

Per cabinet a string of 46 battery blocks is placed and mechanically mounted.

Bypass
Panels + breakers
+

Bypass panels are hung and the battery breakers mounted in the cabinets.

Wiring
Internal + sensors
+

Internal wiring, temperature sensors and network cards are fitted and connected.

//Logistics

Ten pallets staged and supplied in order

Before anything goes on site, the goods run through warehouse inbound and outbound. Ten pallets are checked, bundled and staged in the right order. Transport happens within the delivery radius and on the agreed reception slots.

SITE · AMSTERDAM CSSUPPLY ROUTELOGISTICS & SUPPLY10× PALLET10 PALLETS · INBOUND & OUTBOUNDFIRST CASEFC-2301-01UPS INSTALLATION01 · LOGISTICSSCHAALISO
01Inbound and outbound of ten pallets in the warehouse
02Supply within the fixed delivery radius
03Delivery on fixed days, within work windows 07:00-17:00
//Placement

UPS systems, cabinets and 92 battery blocks in place

On site, two 200 kVA UPS systems and two battery cabinets are set in their final position. Each cabinet takes a string of 46 battery blocks, mechanically mounted and in sequence. The heavy material is brought in over a level, clear floor.

92 BLOCKS · 2 STRINGSPLACEMENT & INSTALLATION92 BLOCKS · 46/STRING2× 200 kVA UPS · 2 CABINETSFIRST CASEFC-2301-02UPS INSTALLATION02 · PLACEMENTSCHAALISO
01Two 200 kVA UPS systems placed
02Two strings of 46 battery blocks in the cabinets
03Access route free of obstacles and level differences
//Finishing

Bypass, sensors and wiring, handed over install-ready

Finally, the bypass panels are hung and the battery breakers mounted. Temperature sensors, network cards and internal wiring are fitted and connected. The whole is handed over install-ready, so Schneider only has to connect and commission.

TEMP SENSORNETWORK CARDBYPASS PANELBREAKERBREAKERBREAKERINSTALL-READYFINISHING & HANDOVERBYPASS · SENSORS · INSTALL-READYFIRST CASEFC-2301-03UPS INSTALLATION03 · FINISHINGSCHAALISO
01Bypass panels hung, breakers mounted
02Temperature sensors and network cards fitted
03Internal wiring connected, handed over install-ready
//The lead time

From order to install-ready handover

After order

Lead time around 5 weeks

Material is ordered and staged, lead time around five weeks.

Warehouse

Inbound and outbound

Ten pallets staged through warehouse inbound and outbound.

On site

Placement

Two UPS systems and two battery cabinets set in position.

On site

Installation

Batteries, bypass panels, breakers and sensors installed.

Handover

Install-ready

Internal wiring connected and handed over install-ready.

The systems stood complete and in the right place when we connected. One party for transport and installation saves us coordination and on-site risk.

Project lead · Schneider
//cases

Other cases

TOTAL MAINTENANCE6× PANEL · ELECTRICALSUPERVISOR-LED CREW · IN OPERATIONFIRST CASEFC-2601-02MAINTENANCE02 · EXECUTIONSCHAALISO
North Holland

Total maintenance of a data center's electrical installation

Total maintenance of the entire electrical installation of a hyperscale data center in North Holland with a fixed supervisor-led crew, more than 200 planned working days over several months.

Electrical Maintenance2026
M10DC CABLING144 CABLES · 95 mm² · M10 CRIMPEDFIRST CASEFC-2502-02UPS & DC CABLING02 · DC CABLINGSCHAALISO
Amsterdam region

12 UPS systems placed and fully DC-cabled

12 Schneider Galaxy VXL UPS systems placed and fully DC-cabled in a colocation data center in the Amsterdam region, 144 cables of 95 mm², every conductor labeled.

Installation2025
FEED5× 200 kW · 1 MW1 REMOTECABLE SETS ≤75 m · UNITS <600 kgFIRST CASEFC-2305-01LOADBANK TESTING01 · SETUPSCHAALISO
Netherlands

New busbar tested with a 1 MW loadbank

A new busbar system tested with a 1 MW loadbank, both feeds loaded separately and in steps, with five compact units under a single remote control.

Loadbank Testing2023