First Case
//Our work

Our projects in production, across all of EMEA.

A selection of the work: UPS installations, battery replacements, monitoring and commissioning in data centers from Amsterdam to Frankfurt. End clients demand that we come.

//Our work

Our projects in production, across all of EMEA.

A selection of the work: UPS, batteries, monitoring and commissioning in data centers from Amsterdam to Frankfurt.

MONITORING6× STRINGS · 30 BLOCSREPLACEMENT & MONITORING11.600+ BLOCKS · PER-BLOCK MONITORINGFIRST CASEFC-2603-02BATTERY REPLACEMENT02 · REPLACEMENTSCHAALISO
FeaturedBattery Replacement · 2026

11.600+ batteries replaced across 50+ UPS systems, Frankfurt

Frankfurt

First Case replaces 11.600+ batteries across 50+ UPS systems at a data center in Frankfurt, from large 1.140 kW units to smaller systems. The work is done per system and string, so the remaining capacity stays available. Each block is connected to continuous per-block monitoring, with a final verification per battery before release.

11.600+
Batteries replaced
50+
UPS systems
100%
Monitored per block
Read the case
MONITORING6× STRINGS · 30 BLOCSREPLACEMENT & MONITORING11.600+ BLOCKS · PER-BLOCK MONITORINGFIRST CASEFC-2603-02BATTERY REPLACEMENT02 · REPLACEMENTSCHAALISO
FeaturedBattery Replacement · 2026

11.600+ batteries replaced across 50+ UPS systems, Frankfurt

Frankfurt

First Case replaces 11.600+ batteries across 50+ UPS systems at a data center in Frankfurt, from large 1.140 kW units to smaller systems. The work is done per system and string, so the remaining capacity stays available. Each block is connected to continuous per-block monitoring, with a final verification per battery before release.

11.600+
Batteries replaced
50+
UPS systems
100%
Monitored per block
Read the case
//All projects
TOTAL MAINTENANCE6× PANEL · ELECTRICALSUPERVISOR-LED CREW · IN OPERATIONFIRST CASEFC-2601-02MAINTENANCE02 · EXECUTIONSCHAALISO
North Holland

Total maintenance of a data center's electrical installation

Total maintenance of the entire electrical installation of a hyperscale data center in North Holland with a fixed supervisor-led crew, more than 200 planned working days over several months.

Electrical Maintenance2026
M10DC CABLING144 CABLES · 95 mm² · M10 CRIMPEDFIRST CASEFC-2502-02UPS & DC CABLING02 · DC CABLINGSCHAALISO
Amsterdam region

12 UPS systems placed and fully DC-cabled

12 Schneider Galaxy VXL UPS systems placed and fully DC-cabled in a colocation data center in the Amsterdam region, 144 cables of 95 mm², every conductor labeled.

Installation2025
FEED5× 200 kW · 1 MW1 REMOTECABLE SETS ≤75 m · UNITS <600 kgFIRST CASEFC-2305-01LOADBANK TESTING01 · SETUPSCHAALISO
Netherlands

New busbar tested with a 1 MW loadbank

A new busbar system tested with a 1 MW loadbank, both feeds loaded separately and in steps, with five compact units under a single remote control.

Loadbank Testing2023
MAIN + DISTRIBUTION BUSBAR~680 mALIGNED · JOINT BY JOINTFIRST CASEFC-2304-02BUSBAR INSTALLATION02 · INSTALLATIONSCHAALISO
Rotterdam

680 m of busbar installed in a Rotterdam data center

Around 680 m of busbar installed in a colocation data center in Rotterdam, including support structure, insulation testing and handover via Site Acceptance Test.

Installation2023
COMPUTER FLOOR · ESD-HEPAFLOOR TILES BOTH SIDES · MAX. 5 AT A TIMEFIRST CASEFC-2503-02DEEP CLEANING02 · DEEP CLEANSCHAALISO
Amsterdam region

Multiple data centers cleaned dust-free, three times yearly

Three times a year ESD- and HEPA-certified deep clean of computer floors, 1.200+ racks and cable trays across multiple data centers of a hyperscaler in the Amsterdam region.

Deep Cleaning2025
DRIVE · 140 mmMAGNETIC LOCKPUSH BUTTON1.200 mmCONTAINMENT DOOR1.200 mm AISLE · ELECTRIC · MAGNETIC LOCKFIRST CASEFC-2602-01CONTAINMENT TURKEY01 · ENGINEERINGSCHAALISO
Turkey

62 automated containment doors produced for Turkey

62 automated containment sliding doors, electric with magnetic lock, produced and delivered export-ready for an existing containment system in a data center in Turkey.

Containment2026
TEMP SENSORNETWORK CARDBYPASS PANELBREAKERBREAKERBREAKERINSTALL-READYFINISHING & HANDOVERBYPASS · SENSORS · INSTALL-READYFIRST CASEFC-2301-03UPS INSTALLATION03 · FINISHINGSCHAALISO
Amsterdam Centraal

UPS installation placed at Amsterdam Centraal station

Transport, placement and mechanical installation of two 200 kVA Schneider UPS systems with 92 battery blocks at Amsterdam Centraal station, handed over install-ready.

Installation2023
CONNECTORS OUT8× STRINGS · 38 BLOCS3× SYSTEM912 BLOCKS OUTFIRST CASEFC-2501-01BATTERY REPLACEMENT01 · DISASSEMBLYSCHAALISO
Amsterdam

912 batteries replaced across three UPS systems

912 batteries replaced across three Galaxy VX 1.500 kVA UPS systems, old blocks recycled under certificate.

Battery Replacement2025
LIMIT VALUE / TYPEMULTIPLE DATA CENTERS36.000+ BATTERIESFIRST CASEFC-2601-01BATTERY MEASUREMENT01 · INVENTORYSCHAALISO
Netherlands

36.000+ batteries measured yearly, estate-wide

Condition of 36.000+ batteries across multiple data centers, measured yearly with report and forecast.

Maintenance2026
//All projects
TOTAL MAINTENANCE6× PANEL · ELECTRICALSUPERVISOR-LED CREW · IN OPERATIONFIRST CASEFC-2601-02MAINTENANCE02 · EXECUTIONSCHAALISO
North Holland

Total maintenance of a data center's electrical installation

2026
M10DC CABLING144 CABLES · 95 mm² · M10 CRIMPEDFIRST CASEFC-2502-02UPS & DC CABLING02 · DC CABLINGSCHAALISO
Amsterdam region

12 UPS systems placed and fully DC-cabled

2025
FEED5× 200 kW · 1 MW1 REMOTECABLE SETS ≤75 m · UNITS <600 kgFIRST CASEFC-2305-01LOADBANK TESTING01 · SETUPSCHAALISO
Netherlands

New busbar tested with a 1 MW loadbank

2023
MAIN + DISTRIBUTION BUSBAR~680 mALIGNED · JOINT BY JOINTFIRST CASEFC-2304-02BUSBAR INSTALLATION02 · INSTALLATIONSCHAALISO
Rotterdam

680 m of busbar installed in a Rotterdam data center

2023
COMPUTER FLOOR · ESD-HEPAFLOOR TILES BOTH SIDES · MAX. 5 AT A TIMEFIRST CASEFC-2503-02DEEP CLEANING02 · DEEP CLEANSCHAALISO
Amsterdam region

Multiple data centers cleaned dust-free, three times yearly

2025
DRIVE · 140 mmMAGNETIC LOCKPUSH BUTTON1.200 mmCONTAINMENT DOOR1.200 mm AISLE · ELECTRIC · MAGNETIC LOCKFIRST CASEFC-2602-01CONTAINMENT TURKEY01 · ENGINEERINGSCHAALISO
Turkey

62 automated containment doors produced for Turkey

2026
TEMP SENSORNETWORK CARDBYPASS PANELBREAKERBREAKERBREAKERINSTALL-READYFINISHING & HANDOVERBYPASS · SENSORS · INSTALL-READYFIRST CASEFC-2301-03UPS INSTALLATION03 · FINISHINGSCHAALISO
Amsterdam Centraal

UPS installation placed at Amsterdam Centraal station

2023
CONNECTORS OUT8× STRINGS · 38 BLOCS3× SYSTEM912 BLOCKS OUTFIRST CASEFC-2501-01BATTERY REPLACEMENT01 · DISASSEMBLYSCHAALISO
Amsterdam

912 batteries replaced across three UPS systems

2025
LIMIT VALUE / TYPEMULTIPLE DATA CENTERS36.000+ BATTERIESFIRST CASEFC-2601-01BATTERY MEASUREMENT01 · INVENTORYSCHAALISO
Netherlands

36.000+ batteries measured yearly, estate-wide

2026
//Next case

Your project, our next case?

From a single UPS to a complete data center. Call us or request a quote and we'll take a look on site.

Response timeWithin 24 hours
Prefer to call?+31 (0)174 221 161