A selection of the work: cabling, UPS installations, battery replacements and measurements in data centers from the Netherlands to Turkey.
A selection of the work: cabling, UPS, batteries and measurements in data centers from the Netherlands to Turkey.
First Case replaces 11.600+ batteries across 50+ UPS systems at a data center in Germany, from large 1.140 kW units to smaller systems. The work is done per system and string, so the remaining capacity stays available. Each block is connected to continuous per-block monitoring, with a final verification per battery before release.
First Case replaces 11.600+ batteries across 50+ UPS systems at a data center in Germany, from large 1.140 kW units to smaller systems. The work is done per system and string, so the remaining capacity stays available. Each block is connected to continuous per-block monitoring, with a final verification per battery before release.
Planned electrical work on the entire electrical installation of a hyperscale data center in the Netherlands with a fixed supervisor-led crew, more than 200 planned working days over several months.
12 UPS systems placed and fully DC-cabled in a colocation data center in the Netherlands, 144 cables of 95 mm², every conductor labeled.
A new busbar system tested with a 1 MW loadbank, both feeds loaded separately and in steps, with five compact units under a single remote control.
Around 680 m of busbar installed in a colocation data center in the Netherlands, including support structure, insulation testing and handover via Site Acceptance Test.
Three times a year ESD- and HEPA-certified deep clean of computer floors, 1.200+ racks and cable trays across multiple data centers of a hyperscaler in the Netherlands.
62 automated containment sliding doors, electric with magnetic lock, produced and delivered export-ready for an existing containment system in a data center in Turkey.
Transport, placement and mechanical installation of two 200 kVA UPS systems with 92 battery blocks at Amsterdam Centraal station, handed over install-ready.
912 batteries replaced across three 1.500 kVA UPS systems, old blocks recycled under certificate.
Condition of 36.000+ batteries across multiple data centers, measured yearly with report and forecast.
From a single UPS to a complete data center. Call us or request a quote and we'll take a look on site.